Project scope consists of roadway, curb and gutter replacement sidewalk repairs, new storm sewer, new water main and parkway restoration. The project improvements include:

. New curb and gutter
· All new asphalt pavement
· Storm sewer replacement and upsizing with new homeowner sewer services
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
· Sidewalk repairs
. Paving of Colfax from Harlem to Nordica

Project Timeline April 2013 – Start of Construction
November 2013 – End of Construction

Friday, June 28, 2013

Storm Sewer along Neva Avenue Continues

This past week the contractor continued to install storm sewer mainline, storm sewer services, and water services along Neva Avenue south of Colfax Avenue. The contractor also perform some preparatory work in advance of installing the internal epoxy liner within the sanitary sewer manholes located in the rear easements.
Next week the contractor will likely complete the installation of storm sewer mainline, storm sewer services, and water services along Neva Avenue south of Colfax Avenue and will begin the same process along Neva Avenue going north of Colfax to Harrison Street.
Currently the contractor will not be working on Thursday, July 4th, but do plan on working on-site Friday, July 5th next week.
During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

Thank you for your patience during the construction operations.